SUBSTANTIATE DOCUMENTS FOR CLAIMING
In the Open Standard
Jack SmithMember for 20 years 7 months
- Created
- 3
- 3
0
HI GUYS,
Anybody have any ideas, under FIDIC "Condition of Contract for Plant and Design-Build for electrical and mechanical works and for building and engineering works designed by the Contractor" First Edition 1999 ........
Where Engineer insturction being issued out appointing xxx consultant as domestic consultant with an agreed price of USD xxxx.xx , and confimed 3% attendance which is issued in accordance with Clause 3.3 of the contract .
Question :
1) Is it necessary to substantiate documents when submitting progress claim for the appointed consultant ??
2) Amount allocated inside the Engineer Instruction , is it subject to changes
Extra ....
A) Sub Contractor for tiling work being appointed as nominated.
B) Tiles supplier being nominated.
C) Our position now is as a Main Contractor. Client required 3% spare materials to be on site upon handover.
Question,
- Estimated Quantity of tiles to be come from Main COntractor or Nominated Tiler.
- If quantity order being more that 3% , and client won’t accept more than 3% who should bear the cost ????
Anybody have any ideas, under FIDIC "Condition of Contract for Plant and Design-Build for electrical and mechanical works and for building and engineering works designed by the Contractor" First Edition 1999 ........
Where Engineer insturction being issued out appointing xxx consultant as domestic consultant with an agreed price of USD xxxx.xx , and confimed 3% attendance which is issued in accordance with Clause 3.3 of the contract .
Question :
1) Is it necessary to substantiate documents when submitting progress claim for the appointed consultant ??
2) Amount allocated inside the Engineer Instruction , is it subject to changes
Extra ....
A) Sub Contractor for tiling work being appointed as nominated.
B) Tiles supplier being nominated.
C) Our position now is as a Main Contractor. Client required 3% spare materials to be on site upon handover.
Question,
- Estimated Quantity of tiles to be come from Main COntractor or Nominated Tiler.
- If quantity order being more that 3% , and client won’t accept more than 3% who should bear the cost ????
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?