Reduction of Quantity of RE Wall
In the Open Standard
Edwin kolandasamyMember for 20 years 11 months
- Created
- 6
- 4
0
Dear All,
Could anyone give me some idea on the case below.
The completed quantity of Reinforced Earth Wall has reduce to half from 75000 sqm(BOQ Quantity) to 35000sqm only? The work is nearly completed to 98%.
We as contractor have written to consultant asking for a increase in unit rate of this item as to recover the loss of profit. It was rejected, reason time barred. Again we wrote proved to the RE that we have not completed the work. Subsequently the engineer said the works was done as per drawing proposed by us. Yes we have submitted the shop drawings or working drawing (draft by an appointed specialist subcontractor in RE wall of India)for approval. It was approved by consultant and client.
We were requested to give reports on the RE Wall panel casting, as on site casting using Concrete Grade 30 was proposed by us. It was approved by Engineer. These casting was closely mointored by the consultant so that we don exceed the required qty.
However our contract is not D&B it just a normal construction of 4 lane road works with bridges, drainage and other road furnitures. Fidic contract.
How shall persue this issue further.
Thanks
Could anyone give me some idea on the case below.
The completed quantity of Reinforced Earth Wall has reduce to half from 75000 sqm(BOQ Quantity) to 35000sqm only? The work is nearly completed to 98%.
We as contractor have written to consultant asking for a increase in unit rate of this item as to recover the loss of profit. It was rejected, reason time barred. Again we wrote proved to the RE that we have not completed the work. Subsequently the engineer said the works was done as per drawing proposed by us. Yes we have submitted the shop drawings or working drawing (draft by an appointed specialist subcontractor in RE wall of India)for approval. It was approved by consultant and client.
We were requested to give reports on the RE Wall panel casting, as on site casting using Concrete Grade 30 was proposed by us. It was approved by Engineer. These casting was closely mointored by the consultant so that we don exceed the required qty.
However our contract is not D&B it just a normal construction of 4 lane road works with bridges, drainage and other road furnitures. Fidic contract.
How shall persue this issue further.
Thanks
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?