Quantity measurement

Mohsin FarooqiMember for 22 years
Created
4
5
0
Dear Fellow Planners
Please give your suggestion for the suspended false ceiling
What are the units of grid whether it should be taken in RMT or SMT?.
And whether deductions for the [Electrical ligts(2’x2’)& A.C diffusers (2’x2’)]same size as that of tiles 2’x2’ should be done while calculating the quantity for false ceiling.

Regards
Mohsin Farooqi

4 replies

Oldest first
  1. 0
    Sathis Jayaweera ·
    Hi mohsin

    What are a RMT and SMT?
    However I understand RMT9 (m. )Is running meter and SMT (m2) square meter pls used universal abbreviation otherwise used full context.
    Whatsoever, your answer shall depend on the method of measurement. Such as SMM7, POMI,ect for building project.
    Ex- in POMI, if the void area less than m2 will not be deduct
  2. 0
    Mohsin Farooqi ·
    Dear satish

    Yes you got it right Running metre and Square metre anyways the Area after deduction is 17000 sft excluding ligts ,the area of ech tile is 4 sft the area of each light is 4 sft x 150 nos = 600 sft, whether this area of 600 sft should be deducted from the total area of 1700 sft ? The grid area and tile area are measured separately In your reply you said the void area less than m2 (in which context with whole area or localised )can you please elaborate on this aspect and The abbreviations you used for measurement SMM7 and POMI please expand it .

    Regards
    Mohsin Farooqi

  3. 0
    Philip Alva ·
    mohsin,

    for info:

    POMI = Principles of Measurement International

    SMM7 = Standard Method of Measurement 7th Edition by RICS

    You have to buy the book for more elaboration.

    Peace!
  4. 0
    Sathis Jayaweera ·

    Hi Moshin

    Philip has given correct answer. Moshin that deduction shall be depend on the method of measurement which adopted in the contract or price preamble.
    If the contract does not mentioned elsewhere then all quantities should be measured as Nett is a best practise.