Delay Due to increased volume of excavation.
In the Open Standard
Pranab Kumar DebMember for 19 years 8 months
- Created
- 8
- 6
0
Dear all,
We have a LUMP SUM project
( the contrat being FIDIC Conditions of Contract
for CONSTRUCTION
FOR BUILDING AND ENGINEERING WORKS
DESIGNED BY THE EMPLOYER)
which had a Tender volume of excavation =4200 m3 whereas the actual volume of excavation was aroun 12,000 m3 . The excavation item being in the critical path the project is presently in delay of around 4 months whereas the total days considered initally for the activity was 35 days it actually took 114 days, please advice how this delay along with damages can be claimed for such the scenario .
The baseline program is in P3.
regards
deb
We have a LUMP SUM project
( the contrat being FIDIC Conditions of Contract
for CONSTRUCTION
FOR BUILDING AND ENGINEERING WORKS
DESIGNED BY THE EMPLOYER)
which had a Tender volume of excavation =4200 m3 whereas the actual volume of excavation was aroun 12,000 m3 . The excavation item being in the critical path the project is presently in delay of around 4 months whereas the total days considered initally for the activity was 35 days it actually took 114 days, please advice how this delay along with damages can be claimed for such the scenario .
The baseline program is in P3.
regards
deb
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?