Excavation below formation
In the Open Standard
Bolisetti JogirajuMember for 19 years 3 months
- Created
- 6
- 4
0
Hi
Friends !
We have a situation like this......
contract is Lump Sum with provisions of variations.
Engineer instructed the contractor to excavate further depth(below formation) due to unsuitability of material.Contractor did it and claims for extra costs of add’l excavation and fill material.
but,Drawing says " fill with type B material as required after,remove all unsuitable/organic soil from site".
Is contractor entitled for his claim ?
Cheers
Friends !
We have a situation like this......
contract is Lump Sum with provisions of variations.
Engineer instructed the contractor to excavate further depth(below formation) due to unsuitability of material.Contractor did it and claims for extra costs of add’l excavation and fill material.
but,Drawing says " fill with type B material as required after,remove all unsuitable/organic soil from site".
Is contractor entitled for his claim ?
Cheers
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?