Change Order VS Variation Order

Pranab Kumar DebMember for 19 years 8 months
Created
8
2
0
Dear All,
I also wanted to know the difference between change order and variation order.
Regards
deb

8 replies

Oldest first
  1. 0
    Anoon Iimos ·
    what does your Contract says?
  2. 0
    Pranab Kumar Deb ·
    Hello Anoon,
    My contract mentions "variation" -any change to the works , which is instructed or approved as a variation under clause 13( Variations and Adjustments ).
    Change order is not mentioned
    regards
    deb
  3. 0
    Anoon Iimos ·
    then you work on Variations and Adjustments, forget Change Orders!
  4. 0
    Pranab Kumar Deb ·
    hello anoon , then tell me what si change order
    regards
    deb
  5. 0
    Anoon Iimos ·
    if it’s defined in your Contract, then that’s the definition, otherwise, forget it! i suppose Variations and Change Orders got the same intent
  6. 0
    Ashraf Jahangeer ·
    Hi Deb,

    Anoon is right as there are also in some contracts like I have a term called "Adjustment Order".

    So it all depends upon how the term is defined in your Contract.

    Regards,

    Ashraf
  7. 0
    Pranab Kumar Deb ·
    Thanks Anoon and Ashraf i believe i got the point.
    regards
    deb
  8. 0
    Ashraf Alawady ·
    No difference in terms of change order and variation order
    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?