Inclement Weather Delays
In the Open Standard
Uri ShacharMember for 23 years 5 months
- Created
- 4
- 5
0
Guys,
my client is working on their project beyond the original timeframe in the Contract, due to Principal delays (assuming I can prove that).
Inclement Weather is defined as a neutral cause of delay in the contract. However, my argument is that my client experienced weather delays during a period outside the original timeframe, in which they worked because of the principal delays, and therefore my client is entitled for the Costs associated with these days as well.
am I correct?
any cases / literature I can rely on?
Thanks!
my client is working on their project beyond the original timeframe in the Contract, due to Principal delays (assuming I can prove that).
Inclement Weather is defined as a neutral cause of delay in the contract. However, my argument is that my client experienced weather delays during a period outside the original timeframe, in which they worked because of the principal delays, and therefore my client is entitled for the Costs associated with these days as well.
am I correct?
any cases / literature I can rely on?
Thanks!
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?