Extension of time due to Exisiting Services
In the Open Standard
Tauqeer SyedMember for 22 years 6 months
- Created
- 10
- 1
0
We outlined reasons which hindered us (the contractor) to perform the work efficiently and in proper sequence and sent our EOT claim to the client. The main reason was the existing of services in a live plant and the Employer did not allow to relocate the existing services on time, so that we could do our civil works.
But now the the client is referring to a clause which according to him clearly identifies and cautions contractor doing the work to cater for lack of continuity and interfaces in the work areas.
We are civil contractor. Is the relocation of existing (live) piping, electrical & instrument services our responsibility? Despite we reminded the client (by letters, weekly and monthly reports.......) that the employer (the owner)is not giving us the work opening?
The client has rejected our EOT, please guide how to reply? (SM please look into it.........)
But now the the client is referring to a clause which according to him clearly identifies and cautions contractor doing the work to cater for lack of continuity and interfaces in the work areas.
We are civil contractor. Is the relocation of existing (live) piping, electrical & instrument services our responsibility? Despite we reminded the client (by letters, weekly and monthly reports.......) that the employer (the owner)is not giving us the work opening?
The client has rejected our EOT, please guide how to reply? (SM please look into it.........)
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?