VARIATIONS ISSUED AFTER THE DATE FOR PC
In the Open Standard
Uri ShacharMember for 23 years 5 months
- Created
- 4
- 5
0
Guys,
The Superintendent issued variations after the approved Date for PC (the Contractor believe the Date for PC should have been extended by the Super).
the Contract provides that the Super can not issue Variations after the Date of PC, which is sensible.
However, what do you think about issuing a Variation after the Date for PC? isn’t that addmission that this date should be extended?
The Superintendent issued variations after the approved Date for PC (the Contractor believe the Date for PC should have been extended by the Super).
the Contract provides that the Super can not issue Variations after the Date of PC, which is sensible.
However, what do you think about issuing a Variation after the Date for PC? isn’t that addmission that this date should be extended?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?