What is start date LOA or Kick off
In the Open Standard
Santhosh kumar NarayananMember for 20 years 2 months
- Created
- 14
- 5
0
One of my contractor claim for EOT on accoun tof late conduct of kick off meeting. We issued LOA (Letter of acceptance) with spcecific start and completion date. The site was ready too - It is internal finishing works, structure hase been done by other contractor- but we conducted kickoff meeitng after 10 days of contractual start date.
Now the contractor is asking for 10 Days EOT and we rejected this based on the the site status as the site was ready to receive the finishing contractor, delay in kickoff meetting is no way holding contractor to start their work.
Please clarify is there any valid ground on contractors claim.
Now the contractor is asking for 10 Days EOT and we rejected this based on the the site status as the site was ready to receive the finishing contractor, delay in kickoff meetting is no way holding contractor to start their work.
Please clarify is there any valid ground on contractors claim.
14 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?