adding subcontractor costs to the claim - recognized?
In the Open Standard
Randal LindleyMember for 19 years 2 months
- Created
- 3
- 1
0
Hi everybody,
Does somebody know perhaps if this is recognized- can a general contractor include in its claim the escalated prices now being charged by the subcontractor?
The Owner (actually the govt in a b.o.t. project) has come out during negotiations and said sorry, but all of the risk of higher wages for your subcontractors were your risk, and that that is the norm for b.o.t. projects.
I’ve just been brought on board to help with the claim, but I am pretty new to this field and still confused- I can prove various substantial delays by the Govt including delays in granting the required building permits, which greatly delayed the actual start of construction in some parts of the Site. These delays took the contractor out of its schedule and were the primary cause for the subcontractors now demanding more money to work on other sections (ie, they realize that things are taking longer and have become more complicated, thereby driving up their costs, so now must charge the contractor more per mile than what the contractor originally estimated vis a vis the govt).
In this case I thought I could say the subcontractors escalated costs could be added to my own to form Direct Costs. But these have been rejected out of hand. Aren’t they valid when the owner is the cause for the price escalation by its delays? And do b.o.t. projects generally mean that the contractor assumes all risk for it subcontractors?
Thanks very much for reading this, I really appreciate it. I am learning that understanding the building of construciton claims is an entire art in itself- very interesting but confusing too. If anyone know of some good case law in this area I’d really appreciate it- have to do some major searching for support.
Thanks again for your time,
Randal
Does somebody know perhaps if this is recognized- can a general contractor include in its claim the escalated prices now being charged by the subcontractor?
The Owner (actually the govt in a b.o.t. project) has come out during negotiations and said sorry, but all of the risk of higher wages for your subcontractors were your risk, and that that is the norm for b.o.t. projects.
I’ve just been brought on board to help with the claim, but I am pretty new to this field and still confused- I can prove various substantial delays by the Govt including delays in granting the required building permits, which greatly delayed the actual start of construction in some parts of the Site. These delays took the contractor out of its schedule and were the primary cause for the subcontractors now demanding more money to work on other sections (ie, they realize that things are taking longer and have become more complicated, thereby driving up their costs, so now must charge the contractor more per mile than what the contractor originally estimated vis a vis the govt).
In this case I thought I could say the subcontractors escalated costs could be added to my own to form Direct Costs. But these have been rejected out of hand. Aren’t they valid when the owner is the cause for the price escalation by its delays? And do b.o.t. projects generally mean that the contractor assumes all risk for it subcontractors?
Thanks very much for reading this, I really appreciate it. I am learning that understanding the building of construciton claims is an entire art in itself- very interesting but confusing too. If anyone know of some good case law in this area I’d really appreciate it- have to do some major searching for support.
Thanks again for your time,
Randal
3 replies
Oldest firstLog in or join to reply