contractual issue
In the Open Standard
Ashraf AlawadyMember for 20 years 1 month
- Created
- 22
- 4
0
Dear all,
can you give me your opinion in the following case:-
The project starting date is 10/11/2005
The project completion date is 09/11/2006
During the construction period there were different delays events , some out side the contractor contraol and caused by others and the majority of the remaining delays events are the contractor own reposibility due to lack of resources and bad manegement.
The engineer has issued many letters to the contractor based on clause 46.1 of the general condition of contract exepressing the engineer concern regarding the contractor delays and low rate of progress due to lack of resources and bad manegement .
In the same time the contractor has sent many letter to the engineer for the delays of other parties and authorities for example to issue the neccessary No Objection Certefecates
to the contractor to start the works in the begening of the projects and some delays from the engineer due to delays in approving the shop drawings and delays in reply to the submitted Requuests for Informations.....etc.
The project has been delayed and actual completion date was 31/07/2007 .
There are meny failure in the quality tsets specially in the asphalt layers and non compliance with the contract specification which give the engineer the wrihgt to instruct the contractor in this stage to reove many areas and to make a major reconstruction works which will cause high cost and need more time from the contractor to do all these rectification works and the engineer has refused the contractor request to hand over the project and to undertake to do all the necceessary rectification works during the early stage of the defects liability period.
To accept that solution the engineer has asked the contractor to drop all his claims.
can you give me your opinion in the following case:-
The project starting date is 10/11/2005
The project completion date is 09/11/2006
During the construction period there were different delays events , some out side the contractor contraol and caused by others and the majority of the remaining delays events are the contractor own reposibility due to lack of resources and bad manegement.
The engineer has issued many letters to the contractor based on clause 46.1 of the general condition of contract exepressing the engineer concern regarding the contractor delays and low rate of progress due to lack of resources and bad manegement .
In the same time the contractor has sent many letter to the engineer for the delays of other parties and authorities for example to issue the neccessary No Objection Certefecates
to the contractor to start the works in the begening of the projects and some delays from the engineer due to delays in approving the shop drawings and delays in reply to the submitted Requuests for Informations.....etc.
The project has been delayed and actual completion date was 31/07/2007 .
There are meny failure in the quality tsets specially in the asphalt layers and non compliance with the contract specification which give the engineer the wrihgt to instruct the contractor in this stage to reove many areas and to make a major reconstruction works which will cause high cost and need more time from the contractor to do all these rectification works and the engineer has refused the contractor request to hand over the project and to undertake to do all the necceessary rectification works during the early stage of the defects liability period.
To accept that solution the engineer has asked the contractor to drop all his claims.
22 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?