contractual milestone
In the Open Standard
Ashraf MokhtarMember for 16 years 9 months
- Created
- 3
- 3
0
the contract has milestone for some stages but one the stages it is not clear in the scope so the client write beside this milestone "if required " when the contractor submit the baseline program he did not include the activities related to this stage while we are reviewing the baseline program we know that this stage is important and it will be needed we ask the contractor to implement this stage in the program as per the contract put he refuse to do so because it is not clear in the scope and he want to submit for EOT after approval of the baseline .... what we should do in this situation?..... please note the contract is re-measurable contract...
thanks all
thanks all