Change in Lump Sum item

Omer HassanMember for 18 years 3 months
Created
2
1
0
Can Engineer increase or decrease the amount of lump sum item through variation clause. If yes then please quote the clause under FIDIC 4th edition reprinted 1992.

Thanks
Omer

2 replies

Oldest first
  1. 0
    Larry Rino ·
    Omer,

    Yes, Engineer can increase or decrease the amount of lump sum item through variation clause 51 of FIDIC 4th ED(1992).

    The Clause 51 does not give any restriction to whether variation should be priced as LS, UP, Daywork, Cost plus, etc.

    I suggest you check other part of your contract, such as special conditions or commercial clarification or price schedule (if any and as long as applicable), for clearer understanding of contract’s rule of pricing a variation.

    Good day...
  2. 0
    Omer Hassan ·
    Thanks Larry, I also think like that.

    Regards,
    Omer