In-Excusable &Excusable delays

Khawaja UddinMember for 20 years 8 months
Created
2
3
0
Can some one please let me know what is difference in In-Excusable and excusable delays.

Thnx & Regards

2 replies

Oldest first
  1. 0
    Ken Sadler ·
    Very simply, an excusable delay is one which is caused by the Employer or is a neutral event (such as adverse weather) for which the Employer takes responsibility.

    An in-excusable delay is one for which the contractor is responsible.

    i.e. generally - excusable delays should provide for an extension of time, in-excusable delays do not
  2. 0
    Ashutosh Nema, PMP ·
    It is just like, mistake done by you is In-Excusable and by your boss is Excusable.