Clause 14 programme or updated programme
In the Open Standard
Kier LegardMember for 20 years 2 months
- Created
- 2
- 1
0
Hi to All,
We submitted a cl14 programme and it was approved by the engineer.The programe has sectional completion dates which is in our contract.
After a few months the engineer told us to revise the program due to change in their requirements,design delay, access dates delay and some delays due to us.They gave us a revised sectional completion dates (a much later date than that in Cl 14 but contract completion date is same.)
Both party agreed to this.
But now the engineer still refers to the old clause 14 in updating the progress and still tell us to use for progress monitoring and call the revised programe as updated programme.
please advice.
Regards,
kier
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?