Increase cost above fixed price allowances
In the Open Standard
Skan BuMember for 20 years 4 months
- Created
- 11
- 4
0
Hi,
A claim for direct consequence of the delay in a project had incurred increase costs due to inflation above its fixed price allowances.
Using BCIS data, how do you work out the inflation allowed?
Say:
Original Contract Sum : £ 20,000,000.00
Deduct Preliminaries: (£ 3,000,000,00)
Deduct 1 Subcontractor Contract Sum: (£ 5,000,000,00)
(Subcontract already claimed
somewhere else? Actual cost?)
------------------
£ 12,000,000,00
------------------
Say the project start in May 06 and original completion October 06 but now complete in May 07
How do you go about working out the adjustment?
Do you use Tender Price Index? or what?
I am totally lost/confuse
or I am barking up the wrong tree all together
Can anyone recommend useful book or articles explaining the use of BCIS data and subject above?
A claim for direct consequence of the delay in a project had incurred increase costs due to inflation above its fixed price allowances.
Using BCIS data, how do you work out the inflation allowed?
Say:
Original Contract Sum : £ 20,000,000.00
Deduct Preliminaries: (£ 3,000,000,00)
Deduct 1 Subcontractor Contract Sum: (£ 5,000,000,00)
(Subcontract already claimed
somewhere else? Actual cost?)
------------------
£ 12,000,000,00
------------------
Say the project start in May 06 and original completion October 06 but now complete in May 07
How do you go about working out the adjustment?
Do you use Tender Price Index? or what?
I am totally lost/confuse
or I am barking up the wrong tree all together
Can anyone recommend useful book or articles explaining the use of BCIS data and subject above?
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?