Special preliminary Item -Time related or value related
In the Open Standard
Rajeshkumar RajendranMember for 20 years 2 months
- Created
- 1
- 4
0
hai everybody,
Lumpsum contract, location Dubai, Fidic (Red book)
in the Prelims (general items), there is one lumpsum item,
FIXED PRICE - LUMP SUM
Access to and possession or use of the site
Refer to Clause 42.1 vol - 1 of Tender and Contract Conditions.
Working space on Site is subject to the reasonable limitations
Imposed by the Engineer
Limitations of Working Hours
Refer to Clause 45.1 vol - 1 of Tender and Contract Conditions
Maintenance of existing services on , under or over the site.
The Contractor shall be responsible for maintaining and
protecting all existing services as specified.
how it will be claimed based on Time Related/Value Related, but nothing is mentioned in Preambles regarding this item
but there is one point
Payment for the following items proceed as lumpsum and shall be paid as a percentage of work completed to total value.
(i) Restrictions
(ii) small plants and tools
Lumpsum contract, location Dubai, Fidic (Red book)
in the Prelims (general items), there is one lumpsum item,
FIXED PRICE - LUMP SUM
Access to and possession or use of the site
Refer to Clause 42.1 vol - 1 of Tender and Contract Conditions.
Working space on Site is subject to the reasonable limitations
Imposed by the Engineer
Limitations of Working Hours
Refer to Clause 45.1 vol - 1 of Tender and Contract Conditions
Maintenance of existing services on , under or over the site.
The Contractor shall be responsible for maintaining and
protecting all existing services as specified.
how it will be claimed based on Time Related/Value Related, but nothing is mentioned in Preambles regarding this item
but there is one point
Payment for the following items proceed as lumpsum and shall be paid as a percentage of work completed to total value.
(i) Restrictions
(ii) small plants and tools
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?