Early Completion Bonuses and Ownership of Float
In the Open Standard
Brennan WestworthMember for 23 years 7 months
- Created
- 6
- 6
0
We have a contract where there is a bonus for early completion but it isnt specific about ownership of float.
My interpretation is that becasue of the early completion bonus, the contractor owns the float because it is worth money (yes I am on the contractor’s team:).
Further to this the contractor should still be entitled to early completion bonus if we can demonstrate that if not for the excusable delays we would have completed early.
Can anyone point me to any cases (preferably in Australia) where a precedent has been set on this issue?
My interpretation is that becasue of the early completion bonus, the contractor owns the float because it is worth money (yes I am on the contractor’s team:).
Further to this the contractor should still be entitled to early completion bonus if we can demonstrate that if not for the excusable delays we would have completed early.
Can anyone point me to any cases (preferably in Australia) where a precedent has been set on this issue?
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?