NEC3 Acceptance of Programme Implications
In the Open Standard
Gary BellMember for 22 years
- Created
- 4
- 3
0
Please can somebody clarify whether or not acceptance of the programme under NEC3 form of contract changes the Works Information?
For example, if a specification (issued with the tender documentation and thus forming part of the Works Information) states one thing, but the programme submitted for acceptance contradicts that information but is acceptable on the basis that it is realistic, does this mean that both parties are contractually obliged to carry out the works in accordance with the Accepted Programme?
For example, if a specification (issued with the tender documentation and thus forming part of the Works Information) states one thing, but the programme submitted for acceptance contradicts that information but is acceptable on the basis that it is realistic, does this mean that both parties are contractually obliged to carry out the works in accordance with the Accepted Programme?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?