Extension of Insurance Policies
In the Open Standard
Sajid BalmaMember for 19 years 4 months
- Created
- 1
- 5
0
Dears
We have a project (FIDIC Silver Book) which is essesntially suspended due to the failure by the employer to provide certain facilities to us to proceed further.
At the start of the project, we have submitted no. of insurances to the Employer. Almost all of them are now expired. The Employer is asking us to renew the policy now. We do not want to as the delays are not our fault and there is a seldom chance that we get any payment if we raise any claim against such extension.
Further, the construction/installatio is 100% achieved.
In view of the above, will someone suggest me if I have any way out of this situation. Please be reminded that active insurance policies are a pre-requisite for any payments.
Regards
We have a project (FIDIC Silver Book) which is essesntially suspended due to the failure by the employer to provide certain facilities to us to proceed further.
At the start of the project, we have submitted no. of insurances to the Employer. Almost all of them are now expired. The Employer is asking us to renew the policy now. We do not want to as the delays are not our fault and there is a seldom chance that we get any payment if we raise any claim against such extension.
Further, the construction/installatio is 100% achieved.
In view of the above, will someone suggest me if I have any way out of this situation. Please be reminded that active insurance policies are a pre-requisite for any payments.
Regards
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?