Responsibility for concurrent delays
In the Open Standard
Bo JohnsenMember for 20 years 7 months
- Created
- 5
- 2
0
Say you have two parties, A and B, and the project has totally suffered 100 days of delays. Party A is responsible for 100 days of delays and party B is responsible for 70 days of delay (i.e. 70 days are concurrent delays).
Who is responsible for what?
1) Party A for all 100 days
2) Party A only for the last 30 days and A+B together for the first 70 days
More importantly does the answer change if party B delayed his activities due to the delays of party A, i.e. no reason to start on his activities if party A not ready anyway (the reason could be for party B to utilize resources on other activities). Say it could be proven that party B delayed his activities by 50 days with purpose, thereby having a total of 20 days of real delays. Party A did not delay anything with purpose, i.e. all 100 days were real delays.
Who is now responsible for what?
1) as above
2) as above
3) Party A for 80 days (30+50) and party B for 20 days (70-50)
4) something else
Best regards,
Bo
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?