from AACEI - 49R-06
Out-of-Sequence Activities
Actual activity progress may override CPM calculation considerations. When actual progress occurs in
activities that should not logically begin due to incomplete preceding activities, this is termed “out-ofsequenceprogress.” The ability of CPM calculations to incorporate and consider the time implications of out-of-sequence progress on activities is essential when considering the activity’s float value. Possible methods to incorporate progress overriding logical necessity include:
• Retained Logic – The data date and all logical relationships are considered and out-of-sequence work is automatically suspended until all logically preceding work is complete.
• Progress Override – The data date is considered but any predecessor relationship to the out-ofsequence activity is completely ignored by the CPM calculations. Note that this does not prevent the software from displaying such relationships as if they were still was in effect.
• Actual Dates – This is a hybrid of the above two methods that retains the predecessor logic if the activity has started out-of-sequence but ignores it if the out-of-sequence activity finishes.
• Constraining All Early Activities – Microsoft Project optionally allows the scheduler to set a status date and then change the CPM calculation options to assign start-no-earlier-than the status date constraints to all unfinished activities that would otherwise show planned work before this date.
• Ignoring the Data Date – By default Microsoft Project ignores status date considerations, thus ignoring the ramifications of out-of-sequence progress. This RP recommends against using any CPM calculations for analysis that do not take into consideration of the effects of the status date to planned work.
This RP recommends the use of retained logic CPM calculation mode due to the fact that logic override
can create orphaned predecessor activities and disregards listed constraints. If the retained logic method
produces poor or inaccurate results, then the logic of the network should be corrected and not the CPM
calculation mode.
SORRY FOR THE POOR FORMATTING BUT PP IS NOT RESPONDING CORRECTLY TO THE FORMATTING AT THE INPUT IT IS NO LONGER WHAT YOU SEE IS WHAT YOU GET