Modified Claims Baseline
- Created
- 15
- 2
Hi All
Seconded to work on a claim - so I do not know the full history etc., nor work for the client - 2 days ago.
Original contractors baseline was very poor - open ends, incorrect logic, SF instead of FS etc. So claims specialist company employed by the contractor who rewrote the baseline adding links, removing links, changing calendar etc., and used Time Impact Analysis to establish the delay. Using this revised programme, after every event, they added the delay and rescheduled then added the next lot of progress and the next event and repeated.
I now have a set of programmes after every event, with this strange logic added FROM the delay events, some of which impact activities by, say, FF 79 days, to an activity that I would not have thought was impacted - e.g. a bad weather delay impacts internal works 9 months later DIRECTLY from the delay event, not through the logic sequencing to get there. Almost all events impact using FF + lag logic and to some really strange successors.
(Activities increased by 325% and relationships by 250% from the revised baseline to the as built programme.)
I now have to counter this arguement. We think that an event only impacted for, say, 5 days not the 25 they suggest. How do I show this? (There are 900+ events!!)
Do I use the revised baseline and remove all odd logic, create a new one and try and figure out the progress, just show a fragnet, base the counter claim on the revised programme being so inaccurate that it is meaningless and therefore the claim is invalid or stick two pencils up my nose and say "Wibble"? Due to the open ends etc., using the original programme will give me I don't know what. Records are missing, progress hase been assumed and estimated so none of that helps.
Or is there some other trick that I am unaware of. All needs to be done in the next 2 weeks or so and will then go before the dispute board (government body).
Any suggestions?
Cheers
Nige
15 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?