Delay in our own activity then further delay not caused by us

Ronn Chester BaluyotMember for 18 years 7 months
Created
4
3
0

Suppose we will do a portion of a superstructure and we will start from excavating the existing foundation done by others. We are already in delay in doing this portion of the superstructure and beacuse of that it became critical. After excavating we found that the foundation does not have the correct setting out and beacuse of that the structural design team need to do a re-design of the superstructure. Remember that we are already in delay but because of this another delay event we will further be delayed. Can we claim an EOT for that? Or the Client can argue that if we started our work on time, when it was not yet critical, then that setting out problem was found out earlier.

4 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·

    Dear RonnMy thought is that

    Dear Ronn

    My thought is that you would need to look at the updated schedule

    1. On the day you should have started the excavation for the PORTION of Superstructure works and see if there was any Float (A) to your part of the activities.
    2. Do an updated schedule on the Day you started excavation and see the current status of the Schedule, if there is any float (B)
    3. No of Days for the Redesign work (C)
    4. Ideally A-B+C should be your entitlement for extension of time.

    However, Senior members maybe better placed to answer to your query.

     

    Best regards

     

    Pranab

  2. 0
    Mike Testro ·

    Hi Ronn This is a classic

    Hi Ronn

    This is a classic case of a Relevant Event Delay occurring during a period of Contractor Culpable Delay.

    (aslo known as the Dot - On pronciple)

    The point turns on whether the Relevant Event Delay caused any further delay.

    If so then the further delay should be added to the completion date as an EoT with costs for that extra period.

    See Balfour Beatty v Chestermount for the ruling.

    Best regards

    Mike Testro

  3. 0
    Nathan Whisson ·

    I would think yes, you can

    I would think yes, you can claim the EOT for the redesign delay only. 

    The way I see it, you used up the float when you got behind and the activity became critical. Since it is generally accepted* that the float belongs to the project (whoever gets to it first, uses it), the fact that the structural re-design became critical is unfortunate (for the Client) but irrelevant and the associated extension of time should be claimable.

    *Unless there is a clause in the contract that says the float belongs to the Client or similar...

  4. 0
    Mike Testro ·

    Hi Nathan Welcome to Planning

    Hi Nathan

    Welcome to Planning Planet.

    Your advice is basically correct but the EoT allowed is the Further Delay Period that extends beyond the Contractor's Delay which is added to the current completion date.

    But then we must remember that this principle is good in English Law and may not extend to the Phillipines or wherever Ronn is now working.

    Best regards

    Mike Testro

Log in or join to reply