EOT for a Particular Section of the Road
- Created
- 2
- 2
Dear All,
I have a problem related to an EOT Claim. Our project is a 10 Km long Highway & there are no sectional project completion dates as per contract.
Currently, work is in progress but behind the schedule. Unfortunately, at the very end sections of the project, we encountered a Unforseen Physical obstruction. So that, now the Engineer is planning to grant a EOT for that particular section (0.50Km) only & has instructed to the contractor to complete the other works (9.50Km) as per contract.
Please clarify whether this is inacordance with the contract or not
Thank You in advance.
Prageeth
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?