Clause 8.3 - The Engineers Notice of Compliance
- Created
- 3
- 1
Dear Members,
Background:
Under FIDIC 1999 terms, unless the Engineer, within 21 days after receiving the programme gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the submitted programme subject to his other obligations under the Contract.
Situation; Programme submitted and excess of 21 days passed without a reply from the engineer. We proceeded in acoordance with the submitted programme and report progress relative to the same. Sometime down the line we recieve the Engineers comments on the programme!
Question:
Should I still comply with his comments that they were recieved after 21 days from submission?
Thanks you
3 replies