Evaluation of EOT Claim and Actual Manpower
In the Open Standard
Dura CellMember for 15 years 10 months
- Created
- 4
- 4
0
All,
The contractor submitted an EOT based on impacted as planned method.
I evaluated using the same method and found out that Contractor is right for the number of days claimed.
Looking on the actual manpower vs. planned manpower, Contractor has only 20 men out of 100 men on the impacted activity.
As a consultant, is it possible to reject Contractor's EOT claim because their actual manpower is less than what was planned?
Thanks in advance