Issue of IFC Drawings without full details.
- Created
- 4
- 4
Dear All,
The problem related to issue of IFC drawings from client.
In Baseline program activity linked with Site handover and issue of IFC Drawings (FS)
Client issued drwaing without proper details (some areas on hold), in programme both IFC and area handover are milestones.
Area handedover 100%. Levels also given.
Contractor already started the work , probem exist while updating the progress how will be the % progress for IFC ?
Option 1: IFC progress 0% and activity % (say 25%) then schedule with progress override . In that case how about the logic ?
Any other scenarios from experts most welcome
Best Regards,
Sunil.