EOT calculation
In the Open Standard
Kannan CPMember for 18 years 4 months
- Created
- 5
- 4
0
Hi All,
In the delay analysis, due to an Employer, delay the Contractor is claiming for for an EOT of 100 days. This is through a certain path in the programme.
At the same data date of above the Contractor is in delay through another path#2 by 40 days.
The above paths are not interlinked. Is the Contractor entitled for entire 100 days with prolongation cost of 60 days? or only entitled for 60 days of EOT and the prolongation cost for 60 days?
Thanks
Best Regards
Kannan