But For Baseline Delay Methodology
- Created
- 1
- 5
I am analyzing a delay claim submitted by a contractor to an Owner. They are using a "But For Baseline" schedule as the basis to measure delay.
The Baseline schedule included closeout activities (60 days) following construction completion to Final Acceptance. The contractor claims the actual duration was only 8 days to complete the closeout activities.
They then revise the Baseline schedule to reduce the closeout duration from 60 days to 8 days. They then measure delays to the as-built schedule.
By using the Buf For Baseline they are increasing the amount of delay claimed by 52 days.
Anyone have experience with this type of methodology? What flaws can we point out with this type of analysis.