Correcting Program for Delay analysis

V KuttyMember for 15 years 9 months
Created
2
5
0

Hi,

I am analysing a program for a dispute. The dispute occured part way through the project so the delays are retrospective but the impact is prospective.

My client, I beleive by accident changed a calendar for a future few activities from a 24x7 to a 8hr/day calendar. Effectively slipping the program by a sizeable chunk of time. Can this calendar be corrected back to 24x7 for an arbitration? will the arbitrator accept such a major correction?

Thanks,

Regards,

Vijay

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi VA flawed baseline

    Hi V

    A flawed baseline programme can be rectified provided the analysts explains why it i necessary.

    The opposition will challenge the correction and the arbitrator will then decide which is preferable.

    Best regards

    Mike T.

  2. 0
    Mike Testro ·

    Hi VAre you acting as an

    Hi V

    Are you acting as an expert witness in an arbitration?

    If so you need to be aware of the special requirements needed for such a position.

    The question that you have just asked indicates that you do not fully understand your role.

    Best regards

    Mike T.