Time scale display problems

Jerome REBOURGMember for 22 years 8 months
Created
2
3
0
Hi there,
I am working on a project beginning in november of 2003 and finishing in july of 2004.
I would like to have a time scale on two level : years, weeks. I want to display weeks’ number from 1 to 52 for each year.

Can someone tell me how to do this?

Thanks a lot

2 replies

Oldest first
  1. 0
    Paul Harris ·
    From the timescale form you should, when using 2002 or 2003 select to show two teirs.

    Then format on Tier to show the Unit of Years with the Label showing the Year date format you require.

    Move to the other Tier select the time Unit of Weeks and scroll down to the bottom of the Label list and select the required Week Numbering format you require. There are lots of options for formatting weeks from the start or end date.

    Unlike P3 you are not able to nominate a date to start the week numbering from.

    Regards
    Paul E Harris
    www.eh.com.au
  2. 0
    Bernard Ertl ·
    Paul, I fixed the link you posted in your signature. The PP forum needs double quotes in the href tag. Bernard Ertl InterPlan Systems Inc. - Project Management Software, Project Planning Software