Effect of Calendars on Task Links
In the Open Standard
Philip RichardsMember for 22 years 10 months
- Created
- 3
- 24
0
can anyone please help?
I have coppied one MS Project into another.
The imported project is working to a different calendar to the master, so I have assigned a ’Task Calendar’ to the imported tasks.
When I compare the imported tasks to the original source programme. there are differences. These appear to occur where there is a lead or lag on the task links.
I assume that the links are not working to the ’Task Calendar’.
Can anybody clarify, and ideally offer a solution?
I have coppied one MS Project into another.
The imported project is working to a different calendar to the master, so I have assigned a ’Task Calendar’ to the imported tasks.
When I compare the imported tasks to the original source programme. there are differences. These appear to occur where there is a lead or lag on the task links.
I assume that the links are not working to the ’Task Calendar’.
Can anybody clarify, and ideally offer a solution?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?