Modifying "Cost"
In the Open Standard
Bob FodenMember for 19 years
- Created
- 3
- 3
0
I have a fairly high level MSP with a number of summary bars that have a lump sum cost against them. There are sub activities but these do not have the costs split out. I want to modify the lump sum cost in the summary line but they are "greyed" out. Does anyone know if this is possible ?
Thanks
Bob
Thanks
Bob
3 replies
Oldest firstLog in or join to reply