Planned Strat / Early Start

Shahzad SikandarMember for 20 years 8 months
Created
2
2
0
What is difference between Planned Start and Early Start dates?

how do i mangage these dates in schedule?

2 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Shahzad,

    By Planned Start, I assume you mean the dates in the ’Start’ column relating to the scheduled dates the tasks are due / planned to begin?

    These dates are determined by MS Project based on a combination of calendar (project or task), precedence (task dependencies) or constraints (ASAP etc).

    The Early Start date are determined by backward and forward passes (ES / EF / LS / LF), taking into account Float (Slack in MS Project). Depending on whether the project is scheduled from the Start Date or a known Finish Date (most are scheduled from the Start Date) the Early Start will be the same as the Planned / Scheduled Start.

    When updating / progressing a schedule you can also use Actual Start, but that’s another story for another time...

    Regards,

    Darren
  2. 0
    Shahzad Sikandar ·
    thanks Kosa