Multiple Projects/Inter Project Links and File Location
In the Open Standard
Mal LeadbetterMember for 25 years 1 month
- Created
- 0
- 5
0
Need some ideas on why this is happening
Using MSP2002 the Project Office has created circa 15 MPP schedules that sit in an overall Master schedule, with a large number of inter project/schedule links. These files are located in the same location on a server, call this the Reporting Location
As part of a programme review, a what if analysis was required. A copy of the files was taken and placed in another directory on the server, call this the What If Location
Now the problem…..
The inter project links, seemingly at random have doubled up ie when looking at activity logic there is a reference to files in the Reporting Location and What If Location.
We have previously relocated the files without the appearance of additional links, however not this time.
We have not been able to replicate the problem as it appears random and does not affect every link and file. I think the issue maybe to do with the acceptance of changed inter project link information, but not sure.
Using MSP2002 the Project Office has created circa 15 MPP schedules that sit in an overall Master schedule, with a large number of inter project/schedule links. These files are located in the same location on a server, call this the Reporting Location
As part of a programme review, a what if analysis was required. A copy of the files was taken and placed in another directory on the server, call this the What If Location
Now the problem…..
The inter project links, seemingly at random have doubled up ie when looking at activity logic there is a reference to files in the Reporting Location and What If Location.
We have previously relocated the files without the appearance of additional links, however not this time.
We have not been able to replicate the problem as it appears random and does not affect every link and file. I think the issue maybe to do with the acceptance of changed inter project link information, but not sure.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?