Durations
- Created
- 2
- 2
hi, I'm an undergrad Mechanical Engineer and I'm having a bit of trouble setting up the durations for a project I'm working on. I have the project starting on 05/12/11 and the first task has duration set to 84 days, however the task is showing as complete by 01/02/12 (61 days latter). I've been trying to sort this out for about an hour and I'm starting to go nuts.
There are 20 tasks in the project with varying durations, none of which are displaying in the project window as lasting as long as they should The whole project should last a little over 4 years and its ending a little after 1, despite having 2 tasks that take over 1000 days.
I'd really appreciate some help with this.
Craig
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?