Headings / Non-Summary tasks without dates / durations etc

Christine PMember for 17 years 5 months
Created
3
3
0

Hi

Is it posible in MSP2013 to make a plain old heading?

I just want a title (not header) above sections of some of my tasks, I don't want a date or duration or anything assigned to them, just a plain old title at certain sections. 

The only thing I've found of help on the internet is to summarise them in a hammock bar.  But that will make my Gantt chart untiday as I dont want hammocks everywhere. 

I know it was do-able in Asta Powerproject, is it possible in MSP please? 

3 replies

Oldest first
  1. 0
    Christine P ·

    I'm guessing it's not

    I'm guessing it's not possible

  2. 0
    Ismet Kocaman ·

    You can enter a placeholder

    You can enter a placeholder task (a manually scheduled task with no duration and start/finish dates, instead, just blank). Set task mode to manual and then format the task name as a header. 

  3. 0
    Christine P ·

    IsmetYou are a gem, thank you

    Ismet

    You are a gem, thank you