Headings / Non-Summary tasks without dates / durations etc
In the Open Standard
Christine PMember for 17 years 5 months
- Created
- 3
- 3
0
Hi
Is it posible in MSP2013 to make a plain old heading?
I just want a title (not header) above sections of some of my tasks, I don't want a date or duration or anything assigned to them, just a plain old title at certain sections.
The only thing I've found of help on the internet is to summarise them in a hammock bar. But that will make my Gantt chart untiday as I dont want hammocks everywhere.
I know it was do-able in Asta Powerproject, is it possible in MSP please?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?