In Actual Duration column Overall duration is showing less

Mukesh Kumar KhatriMember for 13 years 11 months
Created
1
3
0

Hi,

 

I have Master schedule of Project and monthly tracking, updating project, In my project I have inserted columns: Baseline duration, Baseline start and finish, Actual duration and actual start and finsh, In actual duration column overall actual duration is showing 16.18 weeks and its sub tasks (levels) have more duration like 52 weeks, 40 weeks, 20 weeks etc, why showing less in overall? (overall is 16.18 weeks) why?

Please help me if any one know.

Thanks and Regards,

Kumar

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Mukesh, such a large

    Mukesh,

    such a large difference between summary and subordinate tasks duration looks really strange; did you apply specific calendars either to the different projects, or to summary or subordinate tasks?

    Alexandre

Log in or join to reply