I want to display the end date as per Free Slack. How to get the date as per free slack. Further, how to move a task to a free slack finish date without using constraints?
Ex: activity A1 takes 10 days to complete; in sequence, activity A2 takes 100 days to complete. If I plan taking up these two activities in different sections of a Highway, say S1A1, S1A2, S2A1, S2A2.
S1A1 completes after 10days and the resources can move to S2A1 on the 11th day. But S2A2 starts after 100days (completion duration for S1A2), so i want to start S2A1 10 days before S2A2. I dont want to use direct date constraint, Any method like ALAP (ALAP is using Total Float) in MSP for that.
Please help!
Regards
Satish