Skip to content

Split bar

Kannan CPMember for 18 years 4 months
Created
3
4
0

Hi All,

After updating a MS Project Schedule, split bars are visible for the updated activities(i assume due to the logical links). How to avoid it and show a normal current bar for the full remaining duration.

 

Thanks

Best Regards

Kannan

3 replies

Oldest first
  1. 0
    Tom Boyle ·

    Under "Scheduling options for

    Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

    Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

  2. 0
    Tom Boyle ·

    Under "Scheduling options for

    Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

    Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

  3. 0
    Kannan CP ·

    Thanks Tom.

    Thanks Tom.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?