Question about more different projects on one sheet
In the Open Standard
T HeoMember for 10 years 2 months
- Created
- 1
- 2
0
Since a short time I trying to use Ms Project. I can work already a bit with Primavera P6.
Ms Project looks more userfriendly and looks easier to use and build up a single project.
Now my question:
In Primavera I can make different projects and after that I can select different projects and put them in one view. Thats very easy.
How does it work in MS Project?
I have made 2 projects now and I assignments Resources to it and I Gilles. The General calender.. Also I put costs per hour to Every resource (= worker).
In both project are assiged the same resources for some tasks.
1. How can I get both project in one screen?
2. How can I optimize or reschedule both projects when there comes a red man in the task level on the left Side from the task? I mean can Reschulde / optimize the bottle neck ?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?