Gantt Bar duration discrepancy

Bob FodenMember for 19 years 1 month
Created
2
28
0

Dear All,

Can anyone advise how I get the Gantt to display equal duration bars the same length ? I have equal duration activities (12 hours) but the Gantt bar for the activity spanning 20:00 to 08:00 is half the size of the activity spanning 08:00 to 20:00. Both activities have the same 24 hour calendar.

Any assistance would be greatly appreciated.

Work email is bob.foden@partners.basf.com

Thanks

Bob

2 replies

Oldest first
  1. 0
    Tom Boyle ·

    Hi Bob,You'll need to set the

    Hi Bob,

    You'll need to set the lowest tier of your time scale to show units of Hours and a count of 1.  I would also set the corresponding label to None.  Since this essentially wastes the bottom tier, you might need to switch to a 3-tier display.  Once you get what you want, save as a new custom view.  Avoid using the zoom features to control the timescale; instead, directly manipulate the timescale tier units, and adjust the Timescale's Size (i.e. %) property to control the view. 

    Good luck.

  2. 0
    Bob Foden ·

    Thanks Tom

    Thanks Tom