Primary baselines
In the Open Standard
Keith FisherMember for 21 years
- Created
- 6
- 2
0
I have a P3e plan produced on version 4.1 which is ready to be baselined for the first time so i can begin recording progress against it.
The plan already has some progress percentage on some of the activities.
I have saved the plan as a primary baseline, however when i tick the primary baseline box on the column menu the baseline of some of the activities show a baseline with different start and finish dates.
Is it me or should the baseline bars be exactly the same as the activity bars provide i have not progressed any activity since the baseline was saved.
It would apear to be getting data regarding timesacles from somewhere else i.e the original durations. i would of thought that baselining the plan would take a mirror copy of the existing bar lengths and start & finish dates.
Note this only appeas to be happening to activities that had progress prior to being baselined.
Any help /guidence would be appriciated
The plan already has some progress percentage on some of the activities.
I have saved the plan as a primary baseline, however when i tick the primary baseline box on the column menu the baseline of some of the activities show a baseline with different start and finish dates.
Is it me or should the baseline bars be exactly the same as the activity bars provide i have not progressed any activity since the baseline was saved.
It would apear to be getting data regarding timesacles from somewhere else i.e the original durations. i would of thought that baselining the plan would take a mirror copy of the existing bar lengths and start & finish dates.
Note this only appeas to be happening to activities that had progress prior to being baselined.
Any help /guidence would be appriciated
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?