Skip to content

Planned % Variance

Richard BowieMember for 20 years
Created
1
2
0
Hi Guys

In P3e is there a way to read PLANNED % VARIANCE in a report, I’ve tried a few global changes but with no success

any help would be appreciated.
thanks
Richard.

1 reply

Oldest first
  1. 0
    Alex Wong ·
    Richard

    You can display the column call Plan Variance.

    HTH

    Alex

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?