Export & Filters

Mark ChapmanMember for 20 years 5 months
Created
3
1
0
I have moved my project from one computer (old) to another (new)using export and logged in as "admin" user on both machines. I seem to have lost all my filters on the new machine. However when I import a layout, I see the filter is using the old filter and is working correctly despite no reference in the filter table. So what’s happening? My old filters must be hidden so how can I get access to them?

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Mark
    This really is a missing item. It will be included in P6.
    Regards
    Dieter
  2. 0
    A D ·
    The problem still persists. I have already mentioned this problem in another thread, but is there any solution guys??

  3. 0
    Arnold Puy ·
    Hi,

    Based in my experienced in P6, I used to set-up everything including filters and "Save As" the layout as available to "Project".

    Now, everytime I copied the Project & transfer it to another computer, you need to copy as well the necessary layout because, filter is part of that particular layout.

    HTH.

    Arnold