Planned Value Cost Calculation
In the Open Standard
Richard RowberryMember for 23 years 6 months
- Created
- 3
- 3
0
Is there a different calculation in the Planned Value Cost field within the activities view in P3e and the Planned Value Cost field in Projects view? In doing monthly reports, i have some variances between the two sets of figures even though the plan is the same and the baseline attached is the same.
I have checked project settings, Planned Start and Finish Dates, BL start & Finish Dates, BL costs etc. but can’t see why the two values would be different.
Cheers
Richard Rowberry
I have checked project settings, Planned Start and Finish Dates, BL start & Finish Dates, BL costs etc. but can’t see why the two values would be different.
Cheers
Richard Rowberry
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?