Planned Value Cost Calculation

Richard RowberryMember for 23 years 6 months
Created
3
3
0
Is there a different calculation in the Planned Value Cost field within the activities view in P3e and the Planned Value Cost field in Projects view? In doing monthly reports, i have some variances between the two sets of figures even though the plan is the same and the baseline attached is the same.

I have checked project settings, Planned Start and Finish Dates, BL start & Finish Dates, BL costs etc. but can’t see why the two values would be different.

Cheers

Richard Rowberry

3 replies

Oldest first
  1. 0
    James Shimmon ·
    It might be worth checking in the Project view to see whcih baseline is being used for earned value calculations and also which baseline is being used for summary information.

    Shimmo
  2. 0
    John Jeffree ·
    You also need to check that the resource planned dates coincide with the activity planned dates. Don’t forget to summarise open projects. For some reason our P3ec has stopped doing it automatically at the end of the day
  3. 0
    Richard Rowberry ·
    Thanks for the posts guys - I’ll try what you say and let you know