P6 Export to Microsoft Access

Larry CrossMember for 20 years 8 months
Created
1
3
0
Currently using P6 stand alone version. I would like to know if anyone has exported data to Microsoft Access updated in Access then Imported back into P6? We are consindering going to the server based product and Primavera Support has not resloved this issue! Any help would be great appreciated..

1 reply

Oldest first
  1. 0
    Niek Zonneveld ·
    Larry,

    If you use P6 stand alone it does have a DB underneath, likely SQL Server 2005 Express but surely MSDE.

    Why not concentrate your efforts on migrating this DB directly into SQL on you server? I’ve moved Primavera SQL DB’s a few times, and apart from orphaned privuser and pubuser ID issues (which are easy to solve) this works seamlessly.

    Hope this helps,

    Niek.

Log in or join to reply