P5 Allocation Limit

Bryan ArmstrongMember for 19 years 2 months
Created
2
2
0
Could someone please help me, im trying to investigate & workout how the allocation limit is set per project within the web application (The brown line)

2 replies

Oldest first
  1. 0
    Andrew Dick ·
    Bryan,
    What allocation Limit?

    Resource Availability, Role Quantities??

    Also were you aware that in P5 the Web - My Primavera only uses summarised data.

    So you should have a job service set up to summarise your projects each night. Also you should set your ’Level of Summarisation’ at the project level somewhat lower than the ’2’ default if your after any sort of detail.

    Andy
  2. 0
    K D ·
    Hi.
    Allocation limit is set when you use "Planning resource" function (only available in Web module).